Radiant Medical Systems
Coming Soon

Atlantic Canada's most comprehensive community diagnostic imaging center

A state-of-the-art facility is currently under construction at 179 John Yeo Drive, Charlottetown, supporting sustained improved imaging access for Prince Edward Island.

179 John Yeo Drive, Charlottetown
Committed to increasing capacity for Diagnostic Imaging on PEI.
Radiant Medical Systems new facility under construction
Charlottetown, PEI

Built to expand community access to advanced diagnostic imaging across Prince Edward Island.

Construction Progress

The build is taking shape inside and out

Recent progress images from 179 John Yeo Drive show the new facility moving from concept to reality, with framing, mechanical systems, infrastructure preparation, and room-by-room build-out well underway.

Open any image for a full-size view

Wide interior view of the Radiant facility build showing major structural progress
01

A wide progress view inside the facility, showing the scale of the new diagnostic imaging centre taking shape.

Project team meeting around a folding table inside the raw shell of the new facility
02

An early planning session inside the raw shell, before framing and partition work began.

Project team reviewing plans at the start of construction with a scissor lift in the background
03

A walkthrough at the start of construction, with the wide open shell ready for framing to begin.

Mechanical systems and interior framing progressing inside the Radiant facility
04

Mechanical systems and major interior framing advancing across the main build-out.

Interior wall framing and ductwork taking shape inside the new facility
05

Wall framing and overhead infrastructure defining the future clinical layout.

Interior excavation and grading work underway inside the construction site
06

Interior excavation and grading work preparing the slab for core infrastructure.

Sub-slab preparation and service routes being formed inside the new Radiant facility
07

Sub-slab preparation underway as service routes are shaped into the floor plan.

Wood framing defining future rooms in the construction build-out
08

Framed rooms beginning to establish the scale of future diagnostic spaces.

Steel stud framing continuing through rooms and support spaces
09

Steel stud framing continuing through individual rooms and support areas.

Insulation and electrical rough-ins progressing behind partition walls
10

Insulation and electrical rough-ins moving forward behind new partition walls.

Core access and structural openings taking shape inside the facility
11

Core access and structural openings taking shape within the interior build.

Project contractors gathered on-site at the new Radiant facility
12

Contractors from SDI Canada, Richardson Associates, MCA Consultants, and FitzGerald and Snow gathered on-site at the new facility.

Project team members reviewing progress during a walkthrough of the construction site
13

Project team and contractors reviewing progress during a walkthrough of the new facility.

Curved drywall soffit being formed against exposed wood roof framing
14

A curved drywall soffit takes shape against the exposed wood roof framing.

Framed steel doorway opening into a corridor with overhead mechanical and electrical rough-in
15

Looking through a finished steel doorway into a corridor with mechanical and electrical rough-in overhead.

Stainless steel fire doors with closers and panic hardware installed
16

Stainless steel double doors with closers and panic hardware now in place.

Hollow metal door frames installed along a finished drywall corridor
17

Hollow metal door frames installed along a finished drywall corridor.

Interior steel stud framing rising beneath insulated HVAC ductwork
18

Steel stud partition framing rises beneath the main HVAC trunk and insulated supply runs.

Plywood wall sheathing complete with safety harnesses staged and drywall stacked
19

Plywood wall sheathing wrapped, with drywall and safety equipment staged for the next phase.

Pink batt insulation tucked behind steel stud framing as partition walls go up
20

Batt insulation tucked behind steel stud framing as partition walls continue to take shape.

Temporary on-site workstation set against newly framed walls
21

A temporary on-site workstation tucked into a freshly framed area of the build.

Two workers on a scissor lift installing specialty shielding panels on the ceiling
22

Crew on the lift installing the specialty shielding material overhead, one panel at a time.

Specialty shielding material installed across the ceiling above the plywood-clad walls
23

Specialty ceiling shielding now closed in above the plywood-clad walls.

Project team posing together inside the partially framed new facility
24

The project team gathered together for a site photo inside the build.

Worker fitting out a plywood-clad room with the team visible through a window opening
25

Interior fit-out continues in plywood-clad rooms while the team tours the adjoining space.

Project team gathered outside the facility for an on-site discussion
26

A site discussion in the parking lot during a project walkthrough.

Planned Diagnostic Services

A broader imaging vision for the Island

The new centre is being developed to support a more comprehensive outpatient imaging offering in one purpose-built facility.

01

MRI including Cardiac and Prostate MRI

02

Mammography

03

Bone Mineral Density

04

Ultrasound including Echocardiogram

05

Fluoroscopy

06

X-ray

Project Team

The partners shaping the new facility

The construction and design team brings together specialists across architecture, engineering, and delivery.

General Contractors

DJC Construction
FitzGerald and Snow (2010) Ltd.

Architects

Architecture 360 Inc
Nine Yards Architecture

Mechanical Consultants

Looking Ahead

Radiant is building for sustained improved imaging access

This next-phase facility reflects our commitment to strengthening diagnostic imaging capacity on PEI and supporting faster access for patients and clinicians.